Energy Infrastructure · Completed 2025

Meranti Power OCGT Facility

Supporting Architectural Qualified Person for critical energy infrastructure.

Client JEL

Energy InfrastructureJurong Island682 MWSupporting Archi QPWSP Collaboration
Meranti Power hydrogen-ready OCGT facility on Jurong Island
Photo source: AECOM

Project story

Capability in context.

Located on Jurong Island, Meranti Power's 682 MW hydrogen-ready Open Cycle Gas Turbine facility comprises two 341 MW fast-start generating units designed to strengthen Singapore's electricity system resilience.

The facility can respond rapidly when additional generation is required, while its turbines are designed to co-fire up to 30% hydrogen as Singapore prepares for a lower-carbon energy future.

VivATA’s role

Working alongside WSP, VivATA served as the Supporting Architectural Qualified Person for this critical energy infrastructure project.